22 August 2016Print This Post

£13m claim made subject to costs management to ensure it is dealt with justly

Cash flow: case eminently suitable for some degree of control

Cash flow: case eminently suitable for some degree of control

The chief Chancery master has ordered that a case be cost-managed after its £13m value was not disclosed in the claim form, finding that anyway there were “positive reasons why cost management is desirable”.

With estimated costs of more than £4m, Chief Master Marsh said it was “plain that issues of proportionality are engaged”.

He was ruling in Signia Wealth Ltd v Marlborough Trust Company Ltd & Anor [2016] EWHC 2141 (Ch), what he described as a complex and hotly contested case about the departure of the second defendant from her role as CEO of the claimant. The first defendant was the trustee of a trust which held shares in the claimant beneficially for the second defendant and for other family members.

As a preliminary matter, the master was asked whether the case should be subject to costs management. At the time of the hearing, the claimant had incurred costs of £967,000 and forecast expenditure up to the end of the trial of £1,374,000. The defendants had incurred costs of £776,000 with forecast costs being slightly in excess of £1m.

Master Marsh said though there was initial uncertainty, it was now not in doubt that the claim was within the costs management regime, even though it exceeded the £10m threshold for compulsory costs management. “That is so because neither the claim form nor the additional claim mentioned the value of £13m, which is said to be the value of the shares which were held by the first defendant.

“Had the figure been mentioned in the additional claim form, then the costs management regime would not have applied.”

He then went on to look at whether the case should be taken outside the regime, applying the test in CPR 13.15(2).

Master Marsh highlighted five relevant factors. First, the ill-feeling between the parties, serious allegations levelled against the second defendant and the manner in which the litigation was being conducted – “where all proper points are being taken” – made it “eminently suitable for some degree of control by the court”.

Secondly, “on any view, a claim which may be conducted through to a trial lasting ten days with a total cost of £4.14m is an expensive piece of litigation.”

Thirdly, with around £2.4m in costs yet to be expended, it “cannot be said that the court’s ability to control costs would be entirely wasted or largely wasted with such figures involved”.

Fourthly, there was some concern about inequality of arms between the parties, and finally he had regard to the difference in the budgets.

Master Mash concluded: “It is not possible for me to be satisfied here that this litigation can be conducted justly and at proportionate cost without costs management. Although a cost management order will be made at a later stage of the claim than is generally desirable, there are significant future costs to be incurred.

“Indeed, it seems to me that there are positive reasons why cost management is desirable here. The court has power in appropriate cases, and this may well be such a case, to make observations about costs which have been incurred. Without having formed a concluded view on that subject, such observations may be useful here given the size of the incurred costs…

“Overall, it seems to me that there is likely to be a real benefit for the parties if there is a cost management order.”

By Neil Rose


Leave a comment

We encourage you to be part of the Litigation Futures community but please note that all comments will be moderated before posting. We draw your attention to clause 5 of the Terms and Conditions of the site, which deals with user-generated content.